PROJECT AUTHORIZATION PACKET ID: N/A
CONTRACT ID EMARS PROGRAM CODE AUTHORIZATION NO:
      94411 0
It is hereby ordered that the project herein described be undertaken and accomplished within the funding level authorized.
PROJECT ID PROJECT ID NUMBER FEDERAL PROJECT NUMBER 6 YR PLAN ITEM NUMBER 6 YR PLAN ITEM PARENT NUMBER
008 0075 183-184
059 0275 184-186
NHPP 0758 103

06-00079 6-.-
PROJECT TYPE PROJECT LENGTH NUMBER OF BRIDGES SYSTEMS
RECONST TO FREEWAY
PROJECT PHASE
&
RESPONSIBILITY
PLANNING DESIGN RIGHT OF WAY UTILITIES
CONSTRUCTION TITLE DEEDED TO: MAINTENANCE OTHER
FUNDING & TIME
ACCOUNTABILITY
PARTICIPATING AGENCIES
FEDERAL FHWA STATE DOH LOCAL OTHER
REQUESTED FUNDS FOR THIS AUTHORIZATION
ITEM NUMBER PHASE FUND PROGRAM FEDERAL FISCAL YEAR STATE FISCAL YEAR
FEDERAL APPR
CODE
CURRENT FUNDING REQUEST
6-79 D 1200 FD52 2018 2018 Z001 $2,000,000.00
CURRENT FUNDING REQUEST TOTAL: $2,000,000.00
AUTHORIZATION SUMMARY FOR THIS 10-1 SERIES
PHASE TOTAL AUTHORIZATION TO DATE (INCL. CURRENT REQUEST)
PLANNING $0.00
DESIGN $2,000,000.00
UTILITIES $0.00
R/W $0.00
CONSTRUCTION $0.00
NON-HIGHWAYS $0.00
  Total: $2,000,000.00
REMARKS: THIS AUTHORIZATION PROVIDES INITIAL DESIGN FUNDING FOR THE PROJECT. TJ
 
Project Approval Recommended By:
JWM   6/19/2018
Signed and Approved by:
TJ   6/20/2018
AUTHORIZATION LOCATION
ITEM NO. COUNTY DIST FACILITY NAME
ROUTE LENGTH SCOPE
06-00079.00 BOONE
KENTON

6 JUNCTION I-75 & I-275 I- 75 IMPROVE SAFETY, MOBILITY, OPERATIONS, AND GEOMETRICS AT THE JUNCTION OF I-75 AND I-275 AND THE SYSTEM-TO-SYSTEM RAMPS.